September 2016 update

1/9/2016

Comments

 
The focus during the last month has been to talk to landowners about signing the wayleave agreement which needs to be in place before any duct can be laid. So far, almost all those in Old Hutton whose land the route crosses have been visited and have signed. Similarly, one third have signed in Preston Patrick, and visits to owners in New Hutton have started. 

Preparations for installation of the network have begun. The concrete base of the electronics cabinet to be sited behind Old Hutton Public Hall will be constructed at the start of September. Duct is also being laid at four sites where there is building work. Laying duct across fields which will be ploughed and seeded with grass or cereal is a priority because work cannot be done after seeding, possibly causing a year’s delay. Consequently, we are expecting to lay duct in these fields during the week starting 22nd August. Volunteers are needed to help with all duct-laying work so an email appeal will be made a day or two before.

Currently, all signals passing through the B4RN network, which operates in 40+ parishes in Lancashire and Yorkshire, enter the national broadband network at Arkholme and Quernmore. B4RN have announced that they intend to establish a third access point in New Hutton near the Hayclose Lane/A684 junction. The signals will be controlled by the electronics cabinet to be sited in New Hutton. This is important for our network because it will increase its resilience which means it will be more robust if a breakage occurs in the line somewhere, something which is likely to happen during its lifetime of a hundred years.

The next Steering Group meeting will discuss the holding of a public meeting in each parish to discuss the organisation of groups of volunteers in each hamlet and the tasks they will need to do to extend the broadband network from the spur or trunk line on the edge of their hamlet to their houses. Please look out for an email about these meetings which will be sent at about the start of September.

If you have any questions, or want to know who to get in touch with in your parish, please see our contact details.
Comments
    You can see our latest progress here.

    Contact us if you
    want to get involved!

    Archives

    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015

    Categories

    All
    Meeting
    Update

    RSS Feed

Powered by Create your own unique website with customizable templates.